Briefly (as far as possible), what is “STC Camerton” LLC.

The company was organized in 2006 as an organization that deals with the diagnosis and adjustment of rotary equipment (turbines, compressors, exhausters, blowers, large pumps, etc.) and successfully had worked in this direction for more than two years without performing repairs on their own. Of course there were minor works, but I don’t see a rating to list them here.

We  acted as chief engineers, consultants, vibrationers - experts in analyzing and eliminating the causes of increased vibration, balancers, traffic controllers.

Three years ago, in the wake of the crisis, in the spring of 2009, on the recommendation of colleagues and “competitors” of turbinists we work closely with today, some of our employees went to Norilsk, or rather, to the NDP (Norilsk Industrial Region) working at CHP1, CHP2, p / o Taimyr gas-condensate field of OJSC NorilskGazprom, Snezhnogorsk, OJSC Ust-Khanstaiskaya HPP.

Since then, the organization's profile has evolved and expanded in the direction of repairs of power equipment.

Over the past three years, our specialists have participated in such works as:

In the 2009/2010 year. Gardabani, Tbilisi Thermal Power Plant, Georgia. Participated in the overhaul with the replacement and hanging of the blades (with the determination of the moment weight of the blades and their correct distribution by stage) of the last four, exhaust, stages of turbine KT-160-130 turbine turbine, Turboatom plant, power 160 MW. We have performed: sparing the low-pressure rotor with the generator rotor and the high-pressure rotor, inserting a double-flow low-pressure cylinder into the boring, the rotor weight is 36 tons, followed by balancing the entire unit. The total length of shafting more than 25 meters.

In 2010 repair of PR-6 and R-6 Kaluga TZ, through the general contractor.

OJSC "Dneproshina", the scope of work included: repair of the PR-6 control system, with reconfiguration of the security machine and setting up the work of reg. selection, taking into account the wishes of the customer and a complete overhaul of the P-6.

In 2011, routine maintenance of R-6 was carried out in Nikopol, LLC “Heat Generation”, the former shop of the TEC of the Nikopol Pipe Plant, during repair, the first, support-thrust bearing was refueled, with the introduction of the rotor into the old boring, control of changes in the centering and pairing of coupling halves RT-WG, without opening the cylinder. For reference: centering is a combination of rotational axes and geometry.

In 2011, a major overhaul of a mobile gas turbo power plant, PGTS-1500, was carried out on the basis of the gas turbine GTD-1500, the Proletarian SPB plant. Power is 1,5 MW. Repairs included in the scope of work the replacement of five compressor stages and the replacement of turbine blades. Frequency of rotation of the CCD 12600 rpm.

In 2011/2012, they participated in subcontracting to repair the AEG turbine of 1939, 25 MW power at the Sevastopol CHPP, which included: charging the rotor of the generator, pairing the coupling halves of the turbine and the generator, balancing, removing the load and accelerating characteristics of the unit.

In addition to these works, we perform repairs of turbochargers of series K: (K-250, K-500, etc.), repairs of sectional high-pressure pumps, centrifugal pumps, piston compressors, plunger pumps and many other works, some of which can be called exotic.

In conclusion, I would like to hope that after reading you have any questions and a desire to get to know us closer, and maybe even trust your equipment for repairs.